A Photo History of "The Pond"

"This pond will greatly enhance the ability to make snow since the colder the water, the more conducive to snowmaking." (Ed Muzik)

This page will be updated as progress continues.

"Pond construction for the snow making projected started today at Lapham Peak. A pre-construction meeting was held with Waukesha County and Herr Environmental, the contractor for the project. Pond construction commenced immediately after final approval from Waukesha County was given. Herr plans to have the digging and rough grading finished in about two weeks. The final grading and seeding will be done in the spring of 2007."
(John Lupo; Nov. 13, 2006)


Pond construction started on Monday morning (November 13th) following a quick preconstruction meeting and an even quicker "ground breaking ceremony".  In the photo with the gold shovels are L to R:  Leif Hauge, Waukesha County;  John McCarthy, our pond designer; John Lupo, Friends of Lapham Peak; Ed Muzik, LP property manager; Richard Herr, Herr Corporations; Lenny Soto, Herr Corporations.


But first a retaining area had to be built.



The heavy equipment moves in.


Most of the pond will be filled by seepage.

Update November 21, 2006. "The pond construction is on schedule thanks to the good weather. Bob Misslich spoke with Lenny Soto, the backhoe operator, and was told that the pond is about 30% completed at this time. Bob took the following pictures today. Have a happy Thanksgiving everyone." (John Lupo)


November 30, 2006. The pond is almost completed. We got lucky and got an early dump of snow. But, we're on schedule to make snow from the pond by December 11. (Photo by John Lupo.)


November 30, 2006. The pump for the pond has arrived so, hopefully, we'll be able to make enough artificial snow starting on December 11th to keep skiing through New Year's.

December 7, 2006. "The pond construction is almost completed and should be finished on Friday, December 8th. The water pump was delivered earlier this week and the installation will also be done by Herr Construction. Piping will be installed in a trench which will carry water from the pond to the new pump house location. Once completed, the water system will be ready to start pumping water to the snow guns." (John Lupo)

December 7, 2006. Pond completed.


December 13, 2006. Wet well installed. (Photo below by Ed Muzik)


December 31, 2006. "2006 has drawn to a close with the completion of two more components of the pond system. The wet well and connector pipe were installed. The concrete pad was poured for the new pump house location and the wires were pulled for the electrical service. The pump house will be moved to this pad after the January 1 and installation of the pump will begin. The warm weather has helped to keep construction on schedule but it has also cut into the skiing. Don't give up, there is a lot of winter left. Happy New Year everyone." (John Lupo)

  
This page will be updated as progress continues.